We Build Cherry Creek Blog Feature Image

We Build Cherry Creek

We Build Cherry Creek

Cherry Creek has been rapidly growing due to the proximity to downtown Denver and the mix between urban and residential environments, creating a thriving urban district. Recently, there have been numerous projects that graced the neighborhood to enhance the quality of living in the area and GH Phipps is proud to have been part of a few of them.

The North Cherry Creek Business Improvement District serves to make sure that any new construction in the area is operating smoothly for those who live and work there. The district has a comprehensive set of guidelines and procedures to follow during the development of a new project that can be overwhelming if the construction company is not familiar. Rightfully so, the district aims to ensure that construction projects do not interrupt roadways, parking remains relatively open to keep residents and stores happy, and that there is not a large disruption to the neighborhood. Despite the challenges that these necessary guidelines and regulations create, GH Phipps Construction Companies has found productive ways to work alongside the North Cherry Creek Business Improvement District. GH Phipps is excited to be part of these efforts, continuing to focus on serving the needs of the area.

Global Down Syndrome Foundation HQ

The first project GH Phipps completed in the Cherry Creek area was the Global Down Syndrome Foundation Headquarters, an organization dedicated to improving the lives of people with Down Syndrome. The 60,486 SF corporate office building was designed by Saiber Saiber Architects and was constructed for $24.7 million. In addition to the three levels of office space, there is also new first floor retail, a residential level, and two levels of below-grade parking. This building is important to the neighborhood because it not only brought new jobs to the area, but will create continued demand for local talent.

 

This slideshow requires JavaScript.

YETI Storefront

After the completion of the Global Down Syndrome Foundation HQ, we turned our attention to the YETI Storefront. This marks YETI’s first flagship location in the Denver area, who typically sells their coolers, drinkware, and other outdoor gear through retail outlets like REI or Ace Hardware. The construction of the YETI Storefront, which was managed and completed by GH Phipps, marks a strong addition to the shopping district of Cherry Creek.

This slideshow requires JavaScript.

Studio 135

Studio 135 is a new 5-story micro-unit apartment complex located in North Cherry Creek. It features 35 apartments, with 28 of the units consisting of studio and micro floor plans directed toward people working in the Cherry Creek area. GH Phipps served as the General Contractor on a technical zero-lot-line site, meaning that there was no space available to stage or store materials.

For this project, we utilized just-in-time delivery, ensuring materials were brought on-site precisely when they were needed. They were quickly installed, making sure everything was ready for the next day’s deliveries. The build was completed in the fall of 2020 and the structure is currently nearing full occupancy.

Studio 135 in Cherry Creek, Colorado
Studio 135 at 135 Adams St

200 Clayton

Another successful addition to Cherry Creek will be Broe Real Estate Group’s 200 Clayton development. They are an experienced group with a multi-billion dollar portfolio of clients and previous work. This new office is an exciting project we are looking forward to being involved with.

A rendering of 200 Clayton coming soon to the Cherry Creek Neighborhood
A rendering of 200 Clayton coming soon to the Cherry Creek Neighborhood

Throughout all of these projects, GH Phipps has worked seamlessly with the North Cherry Creek Business Improvement District. Our expertise and deep understanding of the construction process within this area have allowed us to meet and exceed our client’s expectations, while strictly adhering to the guidelines and regulations set for us.

If you have any questions regarding construction or development within the North Cherry Creek Business Improvement District, fill out the form below! We would love to work with you on your next project.



GHP - Studio 135: Building in an Urban Environment

Studio 135: Building in an Urban Environment

Studio 135 is a new 5-story micro-unit apartment complex located in North Cherry Creek. It features 35 apartments, with 28 of the units consisting of studio and micro floor plans directed toward people working in the Cherry Creek area. The project was designed by Saiber Saiber Architects and developed by PANDO Holdings, with GH Phipps serving as the General Contractor.

In dense, urban areas like Cherry Creek, the construction process is approached differently than in surrounding suburban areas. In this article, we are going to break down key elements for how we build in a downtown environment.

Considering Communities

Construction can be noisy, invasive, and disruptive to a community. To minimize the impact on a community, open discussion, and careful planning must be prioritized. In Denver specifically, there are many Registered Neighborhood Organizations (RNO’s) that need to be kept in the loop throughout the construction process.

Many areas, such as Cherry Creek, also have Business Improvement Districts (BID’s), which represent commercial property owners in a given area. BID’s have specific construction requirements, including planning for sidewalk and street closures, the impact on parking, and pedestrian safety standards. Understanding these requirements allow us to provide a safe environment while limiting closures and temporary conditions along with the associated costs.

Large building on a street in an urban setting

It is important to maintain a positive relationship with both RNO’s and BID’s throughout both the preconstruction and production phases of a project. Studio 135 is the third of a recent string of projects we’ve built in Cherry Creek. We have also recently completed the Global Downs HQ, a new Yeti retail store, and will soon be constructing an office building for Broe Real Estate Group. Without question, we understand how to meet this need for enhanced communication within the Cherry Creek neighborhood.

Zoning Overlays and Design Advisory Boards

There also has to be a consideration for the area-specific requirements put forth for the neighborhood where construction is taking place. There are often guidelines for the exterior materials, size, height, building setbacks, and ground floor use that can be built in a given area.

Neighborhood plans, zoning overlays, and design advisory boards will define certain uses of a ground floor space, which is often reserved for retail. As developers and their design partners are considering concepts that meet the needs of all these stakeholders, having a partner that can provide quick, reliable cost analysis of alternative solutions can save a lot of valuable time.

Large building in urban area

Relationships with the authorities who issue building permits and perform inspections are also important. Understanding how to balance the cost and schedule benefits of partial permit strategies can dramatically influence how fast a project gets delivered. An advantage of getting phased permits early is being able to streamline the process and start construction while still in the phases of design and development.

However, this can add expenses and delays if design changes need to be made down the line. This holds the potential to force late modifications to the structure’s design as well as the project schedule. Understanding the process of TCO Stocking, TCO, and CO inspections dramatically speed up the owner move-in process, knowing the inspection team is also important.

Logistics

In densely populated urban areas like Cherry Creek, space comes at a premium. There are logistical considerations unique to each construction site that need to be given attention. This can range from details, such as where construction workers are allowed to park, to more serious operational guidelines such as crane location, swing radius, air rights, material deliveries, and trucking routes.

Studio 135 was developed on a zero lot line site, meaning that there was no space available to stage or store materials. When building in a downtown environment, the absence of logistical space leads to more complex scheduling and time constraints. For this project, we utilized just-in-time delivery, ensuring materials were brought on-site precisely when they were needed. They were quickly installed, making sure everything was ready for the next day’s deliveries.

Construction workers on the side of an industrial building

Some building components may also be prefabricated off-site. Prefab systems at Studio 135 included wood-framed structural elements, exterior, and interior wall systems. Utilizing prefab simplifies the construction process, as work is constructed off-site and delivered on-site for installation. We used BIM to design and coordinate the prefabricated wall panels, requiring less on-site labor, a lower staging footprint, and less overall disruption to the community.

The complexity of scheduling and planning was not only relevant to construction methods but also included on-site logistics planning. A parking plan was developed to prevent workers from taking up neighborhood and retail parking. Additionally, the closure of sidewalks, alleys, parking spots, and street lanes required a thoughtful and strategic plan that effectively minimized costs and best-utilized construction time.

In short, building in an urban, downtown environment is no easy task. It takes careful consideration and communication with community organizations, such as RNO’s and BID’s, to get a project off the ground. Construction must comply with zoning requirements, and General Contractors must carefully plan out their work to accommodate the logistical issues unique to each site.